How do you prepare an estimate for renovation or construction?

A step-by-step process covering project details, sections, line items, quantities, rates, contingency, totals and the final review before approval.

How do you prepare an estimate for renovation or construction?

Contents:

  1. What should you define before preparing an estimate?
  2. What information do you need before calculating costs?
  3. How to structure an estimate
  4. How to calculate an estimate in nine steps
  5. How to include and explain contingency and material allowances
  6. Checking the estimate before sending it and tracking revisions
  7. How to prepare estimates faster in the 101 app

What should you define before preparing an estimate?

Before you prepare an estimate, identify the costs you expect for labor, materials and related expenses. For definitions, types of estimates and what the document contains, see our guide to construction estimates. The steps below show how to put an estimate together.

Suppose you have agreed to handle a full bathroom renovation. Check whether waterproofing, relocating connections and removing debris are listed separately in the estimate. When each item shows a quantity and price, the client and contractor can check what is included before they agree on the estimate.

Give each line item a clear name, unit of measure and quantity. This makes the estimate easier to check and leaves less room for different interpretations.

An estimate shows the planned cost of labor and materials. Gather actual costs from receipts and the quantities of work completed, then compare them with the matching line items in the estimate. This shows where costs or quantities changed.

If you use a spreadsheet, check the formulas and keep copies of the approved versions. If your software calculates amounts from quantities and rates, check the line items and the total after it recalculates.

What information do you need before calculating costs?

Gather the information you need before you start the estimate, even if some figures are provisional. With too little information, you may rely on averages that do not reflect conditions on site.

During a site visit, the client may give you the total area, but you may also find recesses, corners, junctions or concealed details. Record each area separately and mark what still needs checking. That way, you can see where each estimated quantity came from.

Collect at least the following information:

  • rooms and work areas, grouped by room, floor or building perimeter
  • measurements and quantities, including areas, perimeters, heights and the lengths of service runs
  • scope of work by stage, such as demolition, preparation, building services and finishes
  • material and brand requirements, or a quality range if no products have been selected
  • site constraints, including elevator access, carrying routes, quiet hours, parking and storage
  • who buys the materials and who handles delivery and carrying them upstairs
  • how the work will be accepted, including stages, sign-off documents, photos and checklists
If you are unsure about a quantity, recheck the measurement before pricing it. If you cannot take the measurement yet, mark the quantity as provisional and note what you need to confirm.

If you need to calculate a quantity on site, see this example using the construction calculator (in Russian). The example opens the calculator in a work report. For your estimate, enter the verified result as the quantity for the relevant line item.

How to structure an estimate

A clear structure makes it easier to refer to the estimate during the job and explain it to the client. A single unsorted list is harder to use on site.

A basic estimate has a header, sections by type of work, line items within those sections and a summary of totals. Use the same sections in a spreadsheet and an estimating app so you can compare versions.

Part of the estimateWhat to includeWhy it matters
HeaderProject, site address, client, contractor, date and versionIdentify the current estimate and keep different projects separate.
SectionsDemolition, preparation, building services, finishes and other expensesReview the work by stage and record sign-off for each stage.
Line itemsDescription, unit of measure, quantity, unit rate, amount and notesCheck each line item independently.
TotalsSection subtotals, grand total and contingencySee the full cost and manage the budget.

It helps to arrange sections in the order the work will happen on site. A typical order is demolition, preparation (floor screed, plastering and partitions), building services (electrical and plumbing), finishes, then other expenses such as delivery, debris removal and equipment rental. This makes the estimate easier to discuss and helps you catch costs that are easy to overlook.

Estimate sheet diagram showing the header, sections, line items and totalsEstimate sheet diagram with labels in Russian.

Give each line item a unit of measure, such as square meters, linear meters, individual units or a whole service. Make sure the unit rate is based on the same unit as the quantity. Otherwise the line total may be wrong even if the rate itself is correct.

How to calculate an estimate in nine steps

Using the same calculation process on different projects makes it easier to compare estimates and spot missing items.

If you start by guessing prices, it will be harder to explain why one room costs more than another. Record the quantities first so the client can follow the calculation.

  1. Record the scope of work, the stages, who buys materials and the quality requirements. These set the boundaries of the estimate that you will review with the client.
  2. Measure the wall, floor and ceiling areas and the lengths of service runs. Count connection points and individual items. Record the results as the starting quantities for the relevant line items.
  3. Organize the estimate into sections for demolition, preparation, building services, finishes and other expenses. This lets you check quantities and costs section by section.
  4. Take the item name, unit of measure and unit rate from the price list. Check that the selected rate matches the work and the unit of measure.
  5. Enter the quantity and multiply it by the unit rate. Record the subtotal on the same line.
  6. Put materials in a separate section or tab. Include the quantity, unit, price, delivery and carrying costs so you can check the cost of purchases separately.
  7. Check related line items, such as primer → plaster → skim coat → paint or cable → conduit → junction boxes → circuit breakers. This helps you find preparatory work or supplies you still need to add.
  8. Show the contingency for unforeseen work and the allowance for extra supplies separately. Record the agreed assumptions used to calculate those amounts and quantities.
  9. Add the line subtotals within each section, then add the section totals. Show the contingency separately and say whether it is included in the grand total. Add the date and version number so everyone can identify the estimate sent for approval.
If you are submitting the estimate for approval before work starts, note that it is based on the information and measurements available at the time. That note helps you distinguish the initial assumptions from later changes.

You can do this in Excel. If you prepare estimates often, using an estimate builder with a library of line items can reduce manual work. It pulls rates from the price list and recalculates the totals. See the guide to using the estimate builder for an example.

How to include and explain contingency and material allowances

A client who sees a contingency line may ask what it covers. At the time of the estimate, the contractor may already know that decisions will come up during the job that cannot yet be priced as specific line items.

Label the contingency clearly and set a limit. You can show it as a percentage or a fixed amount, or tie it to specific risks such as hidden defects, changes to building services or extra components. See our guide to handling unforeseen costs in estimates (in Russian).

Allow for extra material in the quantities when you expect damage, cutting waste, breakage or defects. Track this allowance separately from the contingency for unforeseen work so you can see which risk each covers.

Also check how markups and discounts are handled. If you work from a price list, check whether the markup is included in the unit rate, applied as a multiplier or added to the section total. This helps you apply it only once. A clear price list and automatic totals make it easier for the client to follow the calculation.

Checking the estimate before sending it and tracking revisions

Set aside time to review the estimate before you send it. Catching mistakes at this point can save rework and help prevent disputes when payment for a stage comes due.

Read the estimate from both the client's and the tradesperson's perspective. The client needs to see what is included in the price. The tradesperson needs to know what work to do and how much of it. Clear up anything ambiguous before asking for approval.

  • Check units and quantities. For example, make sure an area measured in square meters has not been entered as a length in linear meters.
  • Check that related work is accounted for, such as surface preparation, priming, leveling and finishing.
  • Check other expenses, including debris removal, delivery, carrying materials upstairs, supplies and equipment rental.
  • If you use Excel, check the formulas and totals. An error in a single cell can affect the grand total.
  • Record the date, version number and what changed.
Put the date and version number in the header, even if you keep everything in one file. They identify the estimate that was approved. The list of changes explains why the new total differs.

For more examples of problems with work descriptions, units, quantities and formulas, see our guide to common estimating mistakes (in Russian).

How to prepare estimates faster in the 101 app

A tradesperson or site supervisor can create an Estimate event in 101 for an individual stage using a smartphone or a browser. The project and expense category identify the site and the type of expense.

Check your permissions and the expense category settings, then choose items from an attached price list or add them manually if allowed. Enter the quantity and check the unit rate and cost. 101 uses these values to calculate the line amounts and total. Save the line items, then save the estimate itself. Reopen the saved estimate to check the result. See the instructions for creating an estimate (in Russian) for the full workflow.

The blog also has a detailed guide to preparing an estimate (in Russian) and an article on preparing a quick estimate (in Russian). They show how to use the structure above in your estimating process.

Estimate cards in 101 alongside a sample consolidated estimate PDFRussian-language example of 101 estimate cards and a consolidated estimate PDF.

You can also ask each specialist to estimate their own scope. The electrician prices the electrical work, the finishing crew prices the finishes, and the plumber prices the plumbing. Combine their estimates in one document. This reduces misunderstandings and helps the estimate reflect the work on site.

If the information changes or additional work comes up, issue a new version and show which line items and amounts changed. Use the agreed version to compare the estimate with actual work and costs as the project progresses.

Once you have the information you need, enter the estimate in 101 estimating software and check the total.